The work on laying a new railway line between gate numbers one and three in Bhagalpur has reached its final stage. On Sunday night, near gate number two, the process of connecting the old and new rails began.
-
New rail line work in Bhagalpur in final stage, track connection work continued overnight
-
Rail tracks being laid after breaking the road near gate number two
-
Major railway preparation, old and new lines being connected in Bhagalpur
The work on laying a new railway line between railway gate number one and railway gate number three in Bhagalpur has now reached its final stage. Late on Sunday night, the railway began work on a crucial part of this project. Near railway gate number two, the road was removed to start the process of connecting the new rail track to the old line.
After around 10:30 PM, railway personnel began breaking the road with the help of excavator machines. The team of railway engineers and staff remained on site late into the night, and construction work continued.
New track already laid for six hundred meters
According to railway officials, about 600 meters of new rail track has already been laid from gate number one to gate number three. Most of the project work is complete, and only the final technical connection remains.
It was reported that near railway gate number two, the old rail line is being connected to the newly laid track. Once this work is complete, the track network necessary for train operations will be ready.
Track connection being done by removing the road
The railway technical team is working on laying sleepers, connecting the rail track, and installing check rails after removing the road. This process is being carried out with great care to ensure no compromise on track quality and safety standards.
Officials say that after connecting the track, inspection and technical testing will also be conducted. Only after meeting all standards will it be approved for operation.
Railway officials present on site
Senior PWI Santosh Kumar was personally supervising the work. He stated that after removing the road, the process of connecting the rail line has begun. All work is being completed quickly according to the planned schedule.
He said that the railway’s priority is to complete the project on time and safely, so that there are no issues in future train operations.
Route closed for safety reasons
For safety during the construction work, movement of people around the work site was restricted. The railway administration had already informed the district administration by letter that the route would be closed from 10 PM for about eight hours.
According to railway officials, after the project is completed, train operations and freight capacity will be further strengthened. Local residents will also benefit from better railway facilities.